Project Execution

In close collaboration, the deugro Hanau and deugro Moscow teams executed the NKNK03 Olefin Project on behalf of Linde Engineering. After intensive planning and engineering, deugro moved nearly 90,000 freight tons of heavy lift and oversized cargo from various origins in the Far East and Europe to a remote job site in Nizhnekamsk, Republic of Tatarstan, Russia.

Industry

Petrochemical

Cargo Highlights

Primary fractionator (724 MT), C3 splitter (525 MT)

Volume

87,350 FRT of heavy lift and oversized refining and processing equipment

Period

March-December 2020

Client

Linde Engineering

deugro Teams

25 experts

Download Case Study