Case Study – Rig move from Germany to Turkey

The Challenges

  • Stringently sequenced delivery requirements
  • Challenging local import requirements
  • Restrictive project schedule
  • Requirement for dynamic and differing delivery solutions due to delayed ground works

Project Execution

The deugro team managed a rig transportation project by road, including accessories, that required an overall flexible, fast, secure and safe handling.

The rig had to be delivered in sequence, starting with the camp facilities for the rig crew and main rig substructure, followed by components such as draw works, mud pumps, and tanks, before ending with the drill pipes.

In addition to the importance of the sequencing, the transit times needed to be factored to ensure timely collection and uninterrupted arrival of these components at the site in order to support the construction sequence as well as prevent site congestion and waiting time.

Industry

Oil and gas

Location

Tekirdag, Turkey

Shipping Period

April to July

Volume

7,610 FRT

Total Truckloads

102 truck movements