Skip links

Case Study – Gullen Range

Project Execution

For one of the world’s leading wind turbine manufacturers, deugro China and Australia moved 73 wind turbines from various loading ports in China to the construction site in New South Wales, Australia. Nine ocean-going vessels had to be chartered to ship the 210,000 freight tons of wind turbine generator (WTG) equipment, including 788 overdimensional components. The biggest items were the blades with a length of 50 meters.

Industry

Wind energy

Chartering

9 full-charter ocean vessels

Volume

210,000 FRT

Biggest Items

Blades of 50 m in length

Cargo Highlights

788 oversized loads

Download Case Study