deugro Delivers Power Transformers for Substation Expansion Project

  • Connect
  • News
  • deugro Delivers Power Transformers for Substation Expansion Project
 

Gothenburg, Sweden, October 12, 2026 – In close collaboration, deugro and dteq Transport Engineering Solutions (dteq) delivered two power transformers to a project site in Scotland.

The transformers were collected at the German manufacturing plant and transported—secured in line with dteq’s load-securing design—to a nearby RO/RO jetty, where they were rolled onto a barge and positioned on pre-installed grillage and stool configurations under the personal supervision of deugro Germany and dteq. After seafastening was installed in accordance with dteq’s engineered design, the barge commenced its three-day Rhine transit to the Port of Rotterdam, the Netherlands, where the transformers were discharged.

For the onward voyage to Scotland, deugro chartered a coaster vessel, onto which the transformers were loaded, stowed and secured in line with dteq’s lifting and load-securing plans, under the personal supervision of dteq and deugro Netherlands. After a three-day voyage, the vessel arrived on schedule at the Port of Leith in Edinburgh, Scotland, where deugro UK coordinated the discharge of both transformers using tandem lifting operations.

For the last mile to the construction site, deugro UK arranged an 18-axle girder frame. With an overall length of more than 64 meters, navigating the 74-kilometer route with the extremely heavy and sensitive units required utmost caution and precision. The route was therefore surveyed in advance for potential obstacles and bottlenecks, while deugro’s project managers personally accompanied the transport, supported by escort vehicles and personnel at the front and rear to ensure a smooth and safe delivery.

Both transformers were delivered safely and on schedule to the site’s designated laydown area and installed in accordance with the project timeline via a single-direction jack-and-skid operation.